An artist rendering of what the new entrance to O'Dowd Hall might look like

  

Oakland University William Beaumont School of Medicine O'Dowd Hall Renovation & Addition

In 2021, 十大菠菜台子保留了Fishbeck+SLAM团队,主要目标是对十大菠菜台子威廉博蒙特医学院在奥多德大厅的空间使用进行研究, 并提出建议,提供更多以问题为基础的独立学习空间,以保持符合其医学教育联络委员会(LCME)的认证.

A significant secondary goal for this proposed project is an enhanced entrance space, 它被称为“门户”,将改善通往O 'Dowd Hall OUWB的可见通道,并为所有游客和居住者提供更多功能. 

The Oakland University Board of Trustees approved the $9.7 million project on June 13, 2022.

Current Status of Renovation & Addition Project
  • (May 10, 2024) The exterior OUWB signage is installed in the new entryway.
  • (April 9, 2024) The new classroom areas are taking shape with paint and carpet completed. 教室的下一步工作包括完成所有的电气和视听技术以及天花板瓷砖. The installation of the moveable classroom walls will occur in May.
  • (March 15, 2024)医学图书馆的装修将于3月15日至31日在安静和协作的大型自习室进行, starting with disassembling of the furniture in the quiet room.
  • (March 14, 2024) In the upcoming weeks, the finishes such as light fixtures, door hardware, and bathroom fixtures will be installed throughout the new areas.
  • (Feb. 9, 2024) Installation began this week on the glass panels, 这是新入口的一个关键设计元素,它将使OUWB在校园中更加引人注目.
  • (Jan. 26, 2024) The metal grid above the elevators is in place and ready for the ceiling to be installed.
  • (Jan. 12, 2024)工作人员已经完成了在入口通道砌体上悬挂胶合板的工作,为下一步:安装金属和不透明玻璃面板做准备.
  • (Dec. 19, 2023)本月将在新的入口通道上完成巨大的楼梯,以及地下电气工程和混凝土地板.
  • (Dec. 1, 2023) The bathroom door frames and the fire alarm system are in place, the exterior brick work is completed, and crews have been installing the classroom door-partition tracks, which are equipped with automatic open and close mechanisms.
  • (Nov. 10, 2023) Interior brick work, drywall installation along with soffit and facia framing have begun.
  • (Nov. 2, 2023) Crews have secured the foundation of the entryway rooftop on the new gateway entrance. Replacement of the heating and cooling unit will begin this month. Patio cleaning is compete and caulking is underway.
  • (Oct. 26, 2023)起重机到达施工现场,允许工作人员在入口通道和入口通道屋顶的基础上添加钢梁.
  • (Oct. 20, 2023) Crews waterproofed the outdoor plaza/patio and indoors, the walls and ceilings were coming into place for the new restrooms on the first floor. 
  • (Oct. 5, 2023)地下管道和内部建筑和机械材料的拆除完成. 内部金属钉框架和新灭火系统的安装工作已接近完成,而内部电力工程仍在进行中. 
  • (Sept. 22, 2023年,建筑工人拆除了二楼的窗户,为增加入口通道的砖石工程扫清道路.
  • (Sept. 8, 2023)在一楼机械区附近安装了一个紧急出口,并在过去几周更新了地下管道的地方更换了内部混凝土工程.
  • (Sept. 1, 2023) Interior metal stud framing is ongoing along with in-wall electrical.
    (You can really see our new classrooms and student study rooms starting to take shape!)
    场地基础将在下周末完成,砖石工程将开始,钢结构安装预计将于本月开始. Demolition of the interior architectural and mechanical materials is completed.
  • (Aug 18, 2023)道奇大厅的拆除工作已经完成,机械/电气行业开始安装他们的新工作. Inside the Medical Library, the walls for the office are roughed in and ready for inspection. Drywall will be installed when the inspection is completed.
  • (Aug. 14, 2023年)-道奇大厅实验室160和162以及医学图书馆办公室的建设计划开始.
  • (Aug. 2, 2023年)- O 'Dowd Hall入口通道上的两棵树被移走,混凝土被拆除,为新入口的基础让路.
  • (July 24, 2023年)-所有奥克兰中心(西)侧的二楼外部入口将保持开放. 电梯只能在第二层到第五层使用,并且只能在这两层之间运行.
  • (July 17, 2023年)-本周将在O 'Dowd Hall前门入口处的施工区域周围安装独立的面板和墙壁. Prep work begins in the Student Lounge to clear the way for the construction of a wall.
  • (May 18, 2023) – Pre-bid meeting for construction companies
  • (May 11, 2023)  Kick-off meeting with American Interiors (furniture vendor)
  • (May 5, 2023) – Completed construction drawings
  • (Sept. 2022 through March 2022) – Focus groups and planning meetings held with students, staff, faculty, OUWB executive leadership, OU Facilities, Fishbeck, and Auch Construction. A town hall for O’Dowd Hall stakeholders was held on Feb. 2, 2023.
  • (September 2022 through March 2022)  Preliminary construction work, soil boring, building inspections, utility testing
  • (Sept. 1, 2022) – Project kick-off meeting held
  • (Aug. 10, 2022) – Bids awarded to Fishbeck (design) and AUCH (construction management
  • (July 20, 2022) – The request for proposals period for construction drawings and construction management ended. 
  • (June 13, 2022) – Project approved by Oakland University Board of Trustees 
  • (Nov. 2021 – May 2022) Project scope and design concept completed

An image of the steel frame under construction

起重机到达施工现场,让工作人员在入口通道和入口通道屋顶的基础上添加钢梁. (Oct. 26, 2023)

An image of the entrance to O'Dowd Hall under construction

Work continues on the new entrance on the east side of O'Dowd Hall. (Photo taken Sept. 28, 2023)

An image of construction underway at O'Dowd Hall

建筑工人拆除了二楼的窗户,为增加入口通道的砖石工程扫清了道路. (Photo taken Sept. 21, 2023)

An image of the entrance to O'Dowd Hall under construction

入口通道的改变包括移走两棵离奥多德大厅门最近的树. (Photo taken Aug. 2, 2023)

An image of O'Dowd Hall construction in July 2023

一楼的走廊上,一名工作人员在一堵临时墙附近工作,墙上有一个通往110间教室的开口. (Photo taken July 28, 2023)

An image of O'Dowd Hall construction in July 2023

The doorway marks the spot for the new Student Lounge entrance. This area is the space that was formerly occupied by the second-floor vending machines. (Photo taken July 28, 2023)

Highlights of the O'Dowd Hall Renovation & Addition Project
  • Addition of a new gateway entrance at the northeast corner of O’Dowd Hall.
  • 新入口内的接待区,非正式的座位,以及通往二楼的开放式楼梯.
  • 进入OUWB医学院学生休息室的入口,位于新楼梯和O 'Dowd房间203和204附近.
  • 五个额外的学生自习室和16个非正式的学生学习空间沿着新的西南走廊.
  • 10个新的小教室(将作为学生学习空间的两倍,类似于110号教室目前的使用方式),能够将8个教室扩展到4个中型教室,可容纳25-30人.
  • Additional offices to house medical education staff in close proximity to the classroom spaces.
  • Updates of existing restrooms.
  • Two additional single-stall, gender-neutral restrooms.
  • A private wellness/lactation room.
  • Outdoor seating near the new gateway entrance.
  • Sitework and parking lot restoration.

An image of a rendering of the new entry

An image of the east study area rendering

A rendering of one of the new hallways

A rendering of the new west study area

Key Future Dates
  • (July 15, 2024) – Occupancy expected prior to 2024-25 academic year

History of O'Dowd Hall

O'Dowd Hall: Past, Present, and Future - A Timeline
An image of O'Dowd Hall under construction
 O'Dowd Hall under construction in 1981. Photo courtesy Oakland University Alumni Association.

O'Dowd Hall is named for Donald O'Dowd and his wife Jan O'Dowd. Donald O'Dowd joined OU in 1960 as a founding faculty member of the university's psychology department. He was appointed as dean of the university in 1961 and served as OU's president from 1970 to 1979. Jan O'Dowd was heavily involved in OU, too, assisting in recruiting faculty and fostering a community including faculty and their families, staff and students.

The 105,占地5000平方英尺的建筑位于十大菠菜台子校园的中心,由五层楼组成. OUWB currently occupies parts of the first, third, and fifth floors, and all of the second and fourth floors. Other spaces in the building are used by the following departments: English; Graduate Program Leadership; Global Management; Modern Languages & Literature; Genetics; and Archeology.

More on the building's past, present, and future:

Nov. 2, 1978 - Groundbreaking ceremony held for O'Dowd Hall.

July 17, 1981 - Building dedication ceremony held. 

2003 - A large 440-seat classroom is converted into three smaller classrooms, each equipped with the latest in AV instructional technology. The classrooms are now lecture halls 202, 203, and 204.

2012 - O'Dowd Hall undergoes a $5.3 million renovation project that includes upgrading the exterior, creation of new breakout rooms, construction of a new student lounge, and room 110 -- a large flexible classroom that can be partitioned into smaller learning spaces. 

Early 2020 - Liaison Committee on Medical Education grants reaccreditation to OUWB. As part of the process, LCME issues OUWB a citation for not having enough space for mid-sized classrooms. A citation does not mean that a medical school is at risk of losing accreditation. Rather, it is an issue that a school is made aware of so it has an opportunity to take corrective actions.

2020-21 - OUWB官员与建筑公司Fishbeck (OUWB认可的建筑供应商之一)合作,进行简短的建筑基础设施评估和规范评估,以确定需要升级的系统,以支持拟议的改造. 一个被称为“门户”的增强入口也被开发出来,以改善进入学校的可见通道. 

June 13, 2022 - Oakland University Board of Trustees approves the $9.7 million renovation project.

July 6, 2022 - OUWB issues request for proposals (RFP) on renovation project.

July 20, 2022 - RFP period closes.

March 2023 - Construction start expected.